Today, throughout the future battery factory completed installation of the heating system and conducted comprehensive testing of boiler equipment and distribution points.
Photo № 1 Bath formation
In addition, work on the internal gas supply to the plant was completed. Gas at the battery plant of Ipower LLC will be used for the production of powder and the operation of chambers for the drying and ripening of plates, on equipment for the production of lead-calcium tape, as well as for individual machines for paston-paste lines and assembly lines. In addition, gas will be used for heating the production building.
Photo № 2 Boiler Room
Also in the production building completed installation of aspiration systems, which consist of:
• gas cleaning equipment
• system automation
• duct system
Exhaust ventilation equipment with a scrubber is mounted at the site of the formation of batteries.
Fully completed work on the connection of water supply for domestic purposes.
In the electrotechnical and electrochemical laboratory, the necessary equipment is fully installed.
On the compliance of the executed works project and the legislation received a positive opinion from the state energy supervision, traffic police and emergencies in:
• boiler
• passing
• administrative-the household case
• transformer substation.
On IPower LLC also completed work on installation of technological equipment, in addition, a large part of the installed equipmenttion is already connected and waiting to start the process of commissioning.
If you have any questions about the construction of IPower LLC can be accessed on an open line that is designed specifically to respond to all public interest issues. The open line is available on the corporate website www.1ak-group.com.
Photo № 3 stretch tape production Ateliers Roche
Photo № 4 Transformer substation
Photo № 5 Workshop production of plates fo batteries