IPower LLC informs about the next stage of construction of a battery factory. At this point, you have completed the installation of foundations for process equipment, installation of interior partitions, work began on the installation of ventilation systems in the production building, produces finishing works (tiles, paint, plaster, ceilings), as well as arrived at the installation of the transformer substation.
Work is continuing in the following areas:
1. Landscaping: installed curbs, they are pouring concrete (6 000 m2), brick paving.
2. Installation of engineering networks (water supply, air supply, electricity, gas, Sewerage, heating, conditioning).
3. Installation of metal tapes on the facade of the administrative building.
4. Floor pouring in axes A-B of the production building.
The project is implemented in accordance with the planned terms of implementation of technical supervision of supervision and control by the Inspectorate of the Department of control and supervision over the construction of the Brest region.
The project implementation began in January 2016, when it was registered as a legal entity", IPower". In 2017 have been passed state examination and received permission to conduct construction works. The project completion is scheduled for late 2018.
Photo of the plant at this stage of construction:
Photo №1 "Work on the landscaping"
Photo No. 2 "Installation of interior partitions"
Photo № 3 "Gender Casting in axes A-B of the production building"
Photo № 4 "Transformer substation"
Photo # 5 "The installation of metal tapes on the facade of the administrative building"
Photo # 6 "The Foundation for process equipment"