IPower LLC informs about the next stage of construction of a battery factory. At the moment (July 12, 2018) installation of transformer substations, installation of internal partitions in the axes-Y 1, the installation of the cassettes on the facade of the administrative building 90% done, work on installation of ventilation systems in the production building.
Work is continuing in the following areas:
1. Landscaping: installed curbs, they are pouring concrete (made 10 000 m2), is laying the paving slabs.
2. Installation of engineering networks (water supply, air supply, electricity, gas, Sewerage, heating, conditioning).
3. Floor pouring in axes A-B and B-In production casing.
4. Finishing works (tiles, paint, plaster, ceilings).
The project is implemented in accordance with the planned terms of implementation of technical supervision of supervision and control by the Inspectorate of the Department of control and supervision over the construction of the Brest region.
The project implementation began in January 2016, when it was registered as a legal entity", IPower". In 2017 have been passed state examination and received permission to conduct construction works. The project completion is scheduled for late 2018.
Photo No. 1 Installation of transformer substations
Photo # 2 floor Filling in the axes of the production building
Photo # 3 Ventilation