Information about the construction of the battery plant IPower LLC , 11.10.2018

IPower LLC informs about the next stage of construction of a battery factory. At this point in the administrative building is completed, all construction, installation and commissioning. Is the delivery of housing in operation.

The installation of engineering networks in the industrial building. At the moment, to the completion of suitable work for the supply of lighting, installed and successfully tested the plumbing, installed ventilation, the facility operates a video surveillance system. In production completed work on laying the polymer coating, the installation of floors in the industrial building is fully completed. At the final stage are the works on the boiler and hydraulic fracturing, object preparing for commissioning.

The construction of the plant continues to install the equipment arrived earlier, also arrived the finishing line and water bath for the formation of the battery. Currently nearing completion of the installation of the mixers, are on the final stage of work on the installation of cameras in advance, which is used for drying and ripening of the electrode plates. Begun installation of production lines of powder. Work continues on installation of the Assembly lines LaPneumatica Italy. Assembly line company LaPneumatica are automated and this enables changeover in minimum time, thus increasing productivity. Begun installation of steel expanded line of Ateliers Roche (France), which is designed to produce grating plates of various sizes as well as line pastanesi Accurate (Denmark). The installation of this equipment started to produce work on the data synchronization lines.

The process of obtaining information on technical conditions issued by state organizations.

The project is implemented inaccording to schedule with the implementation of technical supervision of supervision and control by the Inspectorate of the Department of control and supervision over the construction of the Brest region.

The project implementation began in January 2016, when there were a legal entity IPower LLC. In 2017 have been passed state examination and received permission to conduct construction works. The project completion is scheduled for late 2018.

If you have any questions about the construction of IPower LLC  can be accessed on an open line that is designed specifically to respond to all public interest issues. An open line is available in the rubric "Question-Answer" on the website www.1ak-group. com

Information about the construction of the battery plant IPower LLC , 11.10.2018 - 1

Photo № 1 "The entrance to the administrative building LLC", IPower""

Information about the construction of the battery plant IPower LLC , 11.10.2018 - 2

Photo № 2 "The Corridor of the administrative building IPower LLC"

Information about the construction of the battery plant IPower LLC , 11.10.2018 - 3

Photo № 3 "Boiler Room"

Information about the construction of the battery plant IPower LLC , 11.10.2018 - 4

Photo № 4 "Chamber drying plates"

Information about the construction of the battery plant IPower LLC , 11.10.2018 - 5

Photo № 5 "Еhe electrical Cabinet to connect the production lines of powder"

Information about the construction of the battery plant IPower LLC , 11.10.2018 - 6

Photo № 6 "Mounting Assembly lines LaPneumatica"