The state educational INSTITUTION "Republican centre of the state ecological examination and improvement of professional skill of executives and experts of Ministry" has approved the positive conclusion of the environmental review when considering a construction project at the battery plant LLC IPower.
In the examination of the design documentation "Accumulator plant IPower LLC" with its own boiler to natural gas, address: Brest district, of FEZ "Brest" district "Airport". The amendments" was approved by the positive conclusion of the state ecological expertise. Changes in the project documentation due to clarify the impact of the future plant on the environment based on data from technical data sheets of already-installed equipment purchased in the framework of the investment project. It should be noted that during the finalization of project documentation, special attention was given to questions from the public on this project.
According to the Brest regional Executive Committee: "in conducting the state ecological examination it is established that the solutions contained in the project meet the requirements of the legislation on atmospheric air protection, the law on the protection and use of animal world, law about protection and use of land, the law on the protection and use of subsoil, the legislation on waste management, law on state ecological expertise".
LLC "IPower" it was 29.01.2016 year, in the same year, work commenced on the pre-project documentation on the basis of which was developed by the EIA (impact assessment on environment) organized the public discussion, which resulted in the Protocol of the Commission.
In December 2016, according to the results of the open competitionand was defined by project organization that developed the project and presented it to the state ecological expertise and state expertise of construction. By results of passing examinations were obtained positive conclusions.
On the basis of receiving the necessary permits, construction of facility and purchase of equipment. Carried out appropriate procurement procedure (tender) for choice the General contractor for construction and Assembly works and selection of suppliers for the supply of main technological equipment.
For 2018, the plant supplied with modern equipment of leading world manufacturers of equipment for battery plants:
• LaPneumatica, O. M. I., Sovema (Italy),
• Accurate Product/Moojin/Frimax (Denmark/South Korea/ Spain),
• Sanhuane (China),
• Ekofil'tr (Russia),
• EcoSoft (Ukraine, Italy),
• Digatron (Germany),
• Termotechno (Sweden).
The results of the completion of construction and installation works and a positive environmental review and necessary permits, IPower LLC will begin the stage of carrying out of starting-up and adjustment works.